Define your optimal sprint duration and plan your sprints until project end using Global Sprint Plan Table 1.
| Sprint | Start | Finish |
|---|---|---|
| 1 | 07.03.2019 | 13.03.2019 |
| 2 | 14.03.2019 | 20.03.2019 |
| 3 | 21.03.2019 | 27.03.2019 |
| 4 | 28.03.2019 | 03.04.2019 |
| 5 | 04.04.2019 | 12.04.2019 |
| 6 | 22.04.2019 | 30.04.2019 |
| 7 | 02.05.2019 | 15.05.2019 |
| 8 | 16.05.2019 | 22.05.2019 |
| 9 | 23.05.2019 | 29.05.2019 |
| 10 | 30.05.2019 | 05.06.2019 |
| 11 | 06.06.2019 | 12.06.2019 |
| 12 | 13.06.2019 | 19.06.2019 |
| 13 | 20.06.2019 | 26.06.2019 |
Build your project backlog, including all relevant tasks/deliverables, using Project Backlog Table 2. Prioritize all backlog items (PBI), keeping higher priority items at the top, and lower priority at the bottom.
| PBI | Reaserch and Organization | Status |
|---|---|---|
| A | Sprint Plan | To do |
| B | Gantt Chart | To do |
| C | Technical Research, Literature Review | To do |
| D | Market Research, Existing products | To do |
| E | Business Plan | To do |
| PBI | System Design | Status |
| E | Draft & Blackbox | To do |
| F | Material/Resource analysis/Selection | To do |
| G | Initial Budget Planning | To do |
| PBI | Interim | Status |
| H | Presentation | To do |
| I | Report | To do |
| PBI | Detailed Design | Status |
| J | Design Developement | To do |
| K | Solidworks | To do |
| L | Construction Hardware | To do |
| M | Construction Software | To do |
| N | Material buying | To do |
| O | Assembly | To do |
| PBI | Testing | Status |
| P | Process Testing | To do |
| Q | Functional Tests | To do |
| R | Design change implimentation | To do |
| PBI | Final | Status |
| S | Report | To do |
| T | Video | To do |
| U | Poster | To do |
| W | Presentation | To do |
| X | Manual | To do |
Plan each sprint at its beginning (Sprint Planning session) using the Sprint Plan Table 3.
| Sprint | Task | Responsible | Involved | Status |
|---|---|---|---|---|
| 1 | Sprint Plan | 1 | Julia | team |
| 2 | Gantt Chart | 3 | Julien | - |
| 3 | Technical Research, Literature Review | 1 | Julien | Ronald,Alex |
| 4 | Market Research | 1 | Eren | Maike,Julia |
| 5 | Existing products | 2 | Ronald | Julien |
| 6 | Business Plan | 4 | Alex | Julia |
| 7 | Draft & Blackblox (inititial idea’s) | 2 | Alex | Julien |
| 8 | Material/ Resource analysis/ selection | 4 | Ronald | team |
| 9 | Initial Budget Planning | 2 | Julia | Maike |
| 12 | Presentation | 4 | Julia | team |
| 13 | Report | 2 | Maike | Alex |
| 14 | Design Developement | 4 | Julien | Alex |
| 1 | Solidworks designing | 1 | Alex | - |
| 2 | Construct Hardware | 3 | Ronald | Eren |
| 3 | Develope Software | 1 | Eren | Ronald |
| 4 | Material buying | 1 | Maike | team |
| 5 | Assembly | 2 | Ronald | Julien |
| 6 | Process Testing | 4 | Julien | team |
| 7 | Functional Tests | 2 | Eren | team |
| 8 | Design change implementation | 4 | Eren | team |
| 9 | Report | 2 | Eren | team |
| 12 | Video | 4 | Maike | team |
| 13 | Poster | 2 | Maike | Alex |
| 12 | Presentation | 4 | Julia | team |
| 13 | Manual | 2 | Alex | team |
Review each sprint at its end and update each item status on the Progress Register Table 4.
| Sprint | PBI | Responsible | Involved | Status |
|---|---|---|---|---|
| 1 | Z | X and Y | X, Y, Z, W | Done |
| 2 | K | Z | X, Y, Z, W | Done |
| 3 | D | W, Y and Z | X, Y, Z, W | Done |
| 4 | A | Y | X, Y, Z, W | Done |
| 5 | B | Z and W | X, Y, Z, W | In progress |
| 6 | E | X and W | X, Y, Z, W | In progress |
| 7 | C | Y and Z | X, Y, Z, W | In progress |
Identify key project deliverables (when they will be started and completed) and build a release Gantt chart. See Figure 1 for inspiration.